Construction Updates

Cambridge · Highland Meadows Lot 42 · Current stage: Framing

Pete posts every update as soon as your Construction Manager records it, and shares the same information with your sales consultant, lender and closing coordinator. Your home is at Framing as of Jul 30, 2026.

Update history

Newest first

  1. July 30, 2026

    Framing complete and inspected

    The framing package passed municipal inspection. Roof trusses are set and the home is fully weather-blocked.

  2. July 18, 2026

    Framing underway

    First and second floor walls are standing. Window openings framed per the Cambridge plan.

  3. May 28, 2026

    Foundation completed

    Foundation poured, waterproofed and backfilled. Basement egress window installed.

Progress photos

Only stages your home has reached

Homesite cleared, staked and ready for excavation.
Site Preparation

Homesite cleared, staked and ready for excavation.

Apr 18, 2026 · Michael Ross

Foundation walls poured, waterproofed and backfilled.
Foundation

Foundation walls poured, waterproofed and backfilled.

May 28, 2026 · Michael Ross

Framing and roof trusses complete — first look at your elevation.
Framing

Framing and roof trusses complete — first look at your elevation.

Jul 30, 2026 · Michael Ross

Home fully weather-blocked with window openings framed.
Exterior Progress

Home fully weather-blocked with window openings framed.

Jul 30, 2026 · John Dwyer

Photos are uploaded by your Sales Consultant and Construction Manager.